The Greater Toronto and Hamilton Area continues to grow at a rapid pace, requiring ongoing expansion of the commuter rail service, operated by GO Transit.
Plenary Infrastructure was selected through a competitive process to deliver a new maintenance facility for GO Transit’s commuter rail network.
Location
Whitby, Ontario, Canada
Client
Metrolinx
Value (NPV)
C$859 million
Consortium
Plenary Infrastructure
Plenary Americas' role
Project sponsor
Equity investor
Financial arranger
Co-sponsors
Plenary, Kiewit Canada Development Corp., Bird Capital Limited Partnership
Builder
Bird Design-Build Construction Inc./Peter Kiewit Infrastructure Co.
Architect
Stantec Consulting /ARUP Canada Inc
Services
Honeywell Limited/Toronto Terminals Railway
Financial close date
March 2015
Completion date
March 2018
Contract terms
32.5 years, DBFOM
Awards
Project website
The facility includes approximately 500,000 square feet of new buildings. The project also includes:
The East Rail Maintenance Facility (ERMF) Project is targeting a Gold certification level under the Leadership in Energy and Environmental Design® rating system.
The roof has been surfaced with highly reflective materials that reduce the local heat island effect by significantly limiting absorption of solar radiation.
Rainwater from the PM Bay roof, canopy roof, and consist wash roof (about 10,000 m2 of roof area) will be harvested and reused in wash stations, and administration building washroom flush-fixtures.
The diversion and storage of rainwater contributes to stormwater quality and quantity control and limits the disruption of natural hydrology. The burden on municipal storm water infrastructure is further alleviated by the extensive use of open space vegetated areas and a retention pond.
Bicycle storage and showering facilities, transit access, preferred parking for carpoolers and electric vehicle charging stations have been provided in sufficient quantities and convenient locations to meet the needs of the building occupants.
The East Rail Maintenance Facility is situated in one of the most publicly viewed locations in Whitby. The architecture celebrates the impressive scale of the facility rather than attempt to reduce or mitigate that reality. The singular gesture of the uninterrupted curved roof line and the consistent façade elements combine to create a massing that has a strong sense of presence and identity.
The design for the ERMF facility has taken into consideration the future expansion plans for the site and provided adaptability in the design to accommodate the proposed future works. The contemplated future expansions include a load test cell building, exterior turntable, an additional canopy and track storage, additional progressive maintenance bays, and waste management areas. The current works and facilities were planned such that future construction will minimize the impact on ongoing operations of the ERMF site.
In addition to the future physical expansion of the facility, a thorough consideration of future electrification of the GO Transit system has resulted in a design that allows all necessary work to be carried out at the initial stages of construction, allowing future installation to be carried out with minimal interruption to the operation of the train facility at that time.
At the peak of construction, approximately 1,000 workers were on-site, the majority of which came from the Greater Toronto and Hamilton Areas.
Related projects
The project entails the design, build, finance and maintenance of the new facility constructed for the City-operated transit…
Winnipeg Southwest Rapid Transitway (Stage 2) and Pembina Highway Underpass Project is comprised of significant infrastructure components in…
Plenary, as part of the Grandlinq consortium, has delivered a rapid transit system for the Regional Municipality of…